PGARC Work List – 2020

Priorities

1- NH project – do other on site work at the same time

2- George – end of June (before bugs get bad up there)

3- Fraser Mtn power

4- Pilot, Carney, Tabor, D-Star – work them in around the out of town projects


Projects

    1. George (end of June)

      1. Solar upgrade (equipment on site)

      2. Move antenna to other corner of the building

    2. Fraser

      1. NH project

      2. AC power upgrade

      3. Battery charger

      4. Generator installation

      5. Remove junk building

      6. Remove good building

    3. Tabor

      1. Power upgrade (solar)

      2. Complete the generator installation

      3. Data link from Pilot using our equipment (will be replaced later on NH project)

    4. Pilot

      1. NH project

      2. Batteries

    5. Sinkut

      1. NH project

      2. Charger

    6. Murray Ridge

      1. Battery, charger, fuse panel

    7. Lucille

      1. RF filter to fix Valemount link

      2. Brush clearing

    8. Boer

      1. NH project

      2. Charger

      3. Remove old (unused & bad) antennas

    9. Carney

      1. Change router to NH unit

      2. Fix Internet link to/at EMBC

    10. Other

      1. Move D-Star repeater from UNBC to UHNBC

      2. Remove data link to UNBC